Projects that have been installed, completed and commissioned on site
Development of a phenol extraction unit
Aims at :
Development of a phenol extraction unit and the application of modern technology using N M P solvent
Separation of the fire fighting network from the cooling water network
Aims at :
Raising the pressure of the firefighting network to achieve international standards and raise the degree of protection of equipment and devices that work with petroleum materials
Create a 12 . diameter line
Aims at :
To feed marketing companies with 80 gasoline
Establishment of (2) reciprocating compressors for the ammonia unit in the unit (16)
Aims at:
Maintaining the operating conditions of the unit and raising the cooling efficiency of the ammonia circuit
Establishment of a new turbine line with a diameter of 12 inches and a length of 2 km
Aims at:
To increase the payment rates of the kerosene product from Al-Amriya Company to the Elab Company
HF Establishment of an early warning system for the smuggling of acetic acid
Aims at:
Early detection and suppression of gas leakage to protect equipment and personnel, unit monitoring and remote gas shutdown control
Replacement and renewal of the line 36 inches by unit 16
Aims at:
Early detection and suppression of gas leakage to protect equipment and personnel, unit monitoring and remote gas shutdown control
Cold Box for feeding 2200 m3/h of dry air
Aims at:
Providing the necessary nitrogen to meet the needs of the production units with the appropriate pressure to secure the operating conditions
Modernization of the digital control system alkylbenzene complex
Aims at :
Securing the operational process maintaining the efficiency of the operation of the various production units
Modernization of the digital control system for aromatics complex
Aims at:
securing the operational process – maintaining the efficiency of the operation of the various production units
Unit Propane Compressor (13A)
Aims at:
Maintaining unit operating conditions and increasing pressure from 800: 1400 m3/h
Central Flame Update
Aims at :
Providing the necessary nitrogen to meet the needs of the production units with the appropriate pressure to secure the operating conditions
Ongoing projects
Two reciprocating air compressors for nitrogen production unit
Aims at :
To provide nitrogen in an appropriate quantity and pressure to meet the demands of production units and future uses as well as unit expansions 14
Create, replace and renew both
14, 15 diesel tanks
42 tanks, 43 petrol
Aims at :
Replacement and renewal of existing tanks and towers and increasing the company’s storage capacity
Supply and installation of an automatic warning and extinguishing system for the crude tanker (1, 2, 3, 4, 5, 6)
Aims at :
Achieving safety and industrial security conditions for equipment, personnel, insurance, and protecting tanks from fire
Supply and installation of an automatic alarm and extinguishing system for gasoline tanks (first stage)
Aims at:
Achieving safety and industrial security conditions for equipment, personnel, insurance, and protecting tanks from fire
Complete modernization of the alarm and extinguishing system of the main power station and main transformers
Aims at:
Achieving the conditions of industrial safety and security for equipment and personnel and securing the operational process
Continuous monitoring system for pollutants on the discharge of industrial wastewater and cooling water on Lake Mariout
Aims at:
Early warning of pollutants on the industrial wastewater drainage from the company’s units to avoid leakage problems
Supply and installation of an automatic alarm system for the building (administration – laboratory – safety)
Aims at:
Early warning in the event of fires in the aforementioned buildings
A complete update of the network of fire alarm systems
Aims at:
Achieving the conditions of industrial safety and security for equipment and personnel and securing the operational process
Automatic alarm system and manual extinguishing of vessels and compressors of the company (first stage)
Aims at :
Securing vessels and compressors from the risks of leaks and fires
Automatic foam alarm and extinguishing system for biological treatment and oil separation basins
Aims at:
Achieving the conditions of industrial safety and security for equipment and personnel and securing the operational process
Automatic fire extinguishing system and alarm for stores of make-up and chemicals with foam
Aims at:
Insurance and preservation of the company’s property from fires and recommendations of the company’s civil defense
Complete the cooling water treatment and recovery system (first stage) ZLD
Aims at :
Implementation of the cooling water treatment and recovery system by converting the cooling water into a closed circuit to be retrieved and benefited from